Electrical Load of   (1) 2 No’s of 120KW, 415V motor, 90% Efficiency, 0.8 P.F.  (2) 2 No’s of 150KW, 415V motor, 90% Efficiency, 0.8 P.F.  (3) 100KW, 415V Lighting Load. The targeted P.F. Of system is 0.98     Calculate Size of Discharge Resister for discharging of Capacitor Bank Discharge rate of capacitor is 55v in less than 1 minute. Also calculate reduction in KVAR Rating of capacitor if Capacitor bank is operated at frequency of 30Hz instead of 50Hz and if operating voltage is 390V instead of 415V     Calculation:    For Connection (1):  Total Load KW for Connection (1) =KW / Efficiency=(120×2) / 0.9=266.67KW   Total Load KVAR1= KW×([(√1-(Old P.F.)^2) / Old P.F.] - [(√1-(New P.F.)^2 / New P.F])     Total Load KVAR1=266.67×([(√1-(0.8)^2) / 0.8] - [(√1-(0.98)^2) / 0.98])      Total Load KVAR1=145.98 KVAR    OR      Total Load KVAR1= KW×(tanϕ1- tanϕ2) =266.67×(tan 36.87 - tan 11.48)                ...
  Sizing Of Diesel Generator        Size a diesel generator for following electrical load. Future  load expansion is 20%. Average use of equipment is 0.8.     1) 5 No. of 1 Ph, 230 V, 100 W, CFL bulb, diversity factor is 0.8, starting and running pf is 0.9.   2) 3 No. of 1 Ph, 230 V, 2500 W, Air conditioner with diversity factor of 1, starting and running PF is       0.9.   3) 4 No. of 1 Ph, 230 V, 600 W, halogen lights. Diversity factor is 0.8, starting and running PF is 0.9   4) 2 No. of 3 Ph, 430 V, 15 KW motor with Y-D starter having diversity factor of 0.8, starting P.F is        0.8 and running P.F is 0.9.   5) 2 No. of 3 Ph, 430 V, 100 KW, motor with soft starter having diversity factor of 0.8, starting P.F is      0.8 and running P.F is 0.9              Starting   Current of linear and non-linear loads         Type Of   Load      Equipment      Starting   Current         Linear   Load      General      100% of   full lo...